Subject: Administrative: METOP_M02_ADMIN, Issued: March 03, 2012 This is a multi-part message in MIME format. --------------040509090605030308010900 Content-Type: text/plain; charset=ISO-8859-1; format=flowed Content-Transfer-Encoding: 7bit *Topic: *METOP M02 ADMIN *Date/Time**Issued:*March 03, 2012 1931 UTC* *** *Product(s) or Data Impacted:*METOP** *Date/Time of Initial Impact:*March 03, 2012 19:18:34 UTC* *** *Date/Time of Expected End:*See table in detail for on and off switch times** *Length of Outage:*N/A* * *Details**/Specifics of Change:* 2012/03/03 19:18:34 Seq Nr: 1 Message Nr: 200 ** Metop-A status: A-DCS/2: Nominal AMSUA: Channel 7 noise exceeds specifications ASCAT: Nominal AVHRR: Nominal GRAS: Nominal GOME: Nominal HIRS: Nominal IASI: Nominal MHS: Nominal S&R: Nominal SEM: Nominal ** Direct readout status: LRPT: Off A-HRPT: Regional service transmission schedule for each orbit. ** A-HRPT scheduled activities: Satellite,Orbit,Switch ON,Switch OFF Metop-A,27879,2012-03-04 01:30:32,2012-03-04 01:51:18,A Metop-A,27880,2012-03-04 02:35:52,2012-03-04 02:43:28,D Metop-A,27880,2012-03-04 03:14:12,2012-03-04 03:32:39,A Metop-A,27880,2012-03-04 04:15:08,2012-03-04 04:24:50,D Metop-A,27881,2012-03-04 04:54:46,2012-03-04 05:18:18,A Metop-A,27881,2012-03-04 05:51:39,2012-03-04 06:06:25,D Metop-A,27882,2012-03-04 06:34:40,2012-03-04 06:59:40,A Metop-A,27882,2012-03-04 07:28:36,2012-03-04 07:49:19,D Metop-A,27883,2012-03-04 08:12:49,2012-03-04 08:31:59,A Metop-A,27883,2012-03-04 09:11:21,2012-03-04 09:31:46,D Metop-A,27884,2012-03-04 09:53:51,2012-03-04 10:09:11,A Metop-A,27884,2012-03-04 10:54:01,2012-03-04 11:13:07,D Metop-A,27885,2012-03-04 11:35:12,2012-03-04 11:48:51,A Metop-A,27885,2012-03-04 12:36:01,2012-03-04 12:54:29,D Metop-A,27886,2012-03-04 13:17:54,2012-03-04 13:31:14,A Metop-A,27886,2012-03-04 14:17:23,2012-03-04 14:35:50,D Metop-A,27887,2012-03-04 15:03:43,2012-03-04 15:14:59,A Metop-A,27887,2012-03-04 15:58:45,2012-03-04 16:17:12,D Metop-A,27888,2012-03-04 16:45:05,2012-03-04 16:58:45,A Metop-A,27888,2012-03-04 17:35:49,2012-03-04 17:58:34,D Metop-A,27889,2012-03-04 18:26:27,2012-03-04 18:48:06,A A 1-burn in-plane manoeuvre was executed on 2012-03-02. The new orbit is: 1 29499U 06044A 12064.25000000 .00000000 00000+0 42384-4 0 00015 2 29499 98.7139 124.9119 0001020 45.3129 323.0605 14.21490385278829 ** ASCAT monthly calibration ** Calibration activities are foreseen between 2012-03-02 and 2012-03-05. Interrruptions scheduled: 2012-03-04 08:15:01 orbit 27883 2012-03-05 19:15:39 orbit 27904 *Contact Information for Further Information:* ESPC Operations at ESPCOperations@noaa.gov and 301-817-3880 *Web Site(s) for applicable information:*N/A This message was sent from ESPC.Notification@noaa.gov. You have been sent this and other notifications because you have opted in to receive it. If for any reason, you wish to unsubscribe, please contact ESPC Help Desk at ESPCOperations@noaa.gov or (301) 817-3880. Please note: it make take up to two business days to process your unsubscribe request. --------------040509090605030308010900 Content-Type: text/html; charset=ISO-8859-1 Content-Transfer-Encoding: 7bit Topic:  METOP M02 ADMIN

Date/Time Issued:  March 03, 2012 1931  UTC

Product(s) or Data Impacted:  METOP

Date/Time of Initial Impact:  March 03, 2012  19:18:34  UTC

Date/Time of Expected End:  See table in detail for on and off switch times

Length of Outage:  N/A

Details/Specifics of Change:

2012/03/03 19:18:34

Seq Nr: 1
Message Nr: 200

** Metop-A status:
A-DCS/2: Nominal
AMSUA: Channel 7 noise exceeds specifications
ASCAT: Nominal
AVHRR: Nominal
GRAS: Nominal
GOME: Nominal
HIRS: Nominal
IASI: Nominal
MHS: Nominal
S&R: Nominal
SEM: Nominal
** Direct readout status:
LRPT: Off
A-HRPT: Regional service transmission schedule for each orbit.
** A-HRPT scheduled activities:
Satellite,Orbit,Switch ON,Switch OFF
Metop-A,27879,2012-03-04 01:30:32,2012-03-04 01:51:18,A
Metop-A,27880,2012-03-04 02:35:52,2012-03-04 02:43:28,D
Metop-A,27880,2012-03-04 03:14:12,2012-03-04 03:32:39,A
Metop-A,27880,2012-03-04 04:15:08,2012-03-04 04:24:50,D
Metop-A,27881,2012-03-04 04:54:46,2012-03-04 05:18:18,A
Metop-A,27881,2012-03-04 05:51:39,2012-03-04 06:06:25,D
Metop-A,27882,2012-03-04 06:34:40,2012-03-04 06:59:40,A
Metop-A,27882,2012-03-04 07:28:36,2012-03-04 07:49:19,D
Metop-A,27883,2012-03-04 08:12:49,2012-03-04 08:31:59,A
Metop-A,27883,2012-03-04 09:11:21,2012-03-04 09:31:46,D
Metop-A,27884,2012-03-04 09:53:51,2012-03-04 10:09:11,A
Metop-A,27884,2012-03-04 10:54:01,2012-03-04 11:13:07,D
Metop-A,27885,2012-03-04 11:35:12,2012-03-04 11:48:51,A
Metop-A,27885,2012-03-04 12:36:01,2012-03-04 12:54:29,D
Metop-A,27886,2012-03-04 13:17:54,2012-03-04 13:31:14,A
Metop-A,27886,2012-03-04 14:17:23,2012-03-04 14:35:50,D
Metop-A,27887,2012-03-04 15:03:43,2012-03-04 15:14:59,A
Metop-A,27887,2012-03-04 15:58:45,2012-03-04 16:17:12,D
Metop-A,27888,2012-03-04 16:45:05,2012-03-04 16:58:45,A
Metop-A,27888,2012-03-04 17:35:49,2012-03-04 17:58:34,D
Metop-A,27889,2012-03-04 18:26:27,2012-03-04 18:48:06,A
A 1-burn in-plane manoeuvre was executed on 2012-03-02.
The new orbit is:
1 29499U 06044A   12064.25000000  .00000000  00000+0  42384-4 0 00015
2 29499  98.7139 124.9119 0001020  45.3129 323.0605 14.21490385278829
** ASCAT monthly calibration **
Calibration activities are foreseen between 2012-03-02 and
2012-03-05. Interrruptions scheduled:
2012-03-04 08:15:01 orbit 27883
2012-03-05 19:15:39 orbit 27904



Contact Information for Further Information: ESPC Operations at ESPCOperations@noaa.gov and 301-817-3880

Web Site(s) for applicable information: N/A

This message was sent from ESPC.Notification@noaa.gov. You have been sent this and other notifications because you have opted in to receive it. If for any reason, you wish to unsubscribe, please contact ESPC Help Desk at ESPCOperations@noaa.gov or (301) 817-3880. Please note: it make take up to two business days to process your unsubscribe request.
    

 

--------------040509090605030308010900--