Subject: Administrative: Update #! ESPC server rack realignment on This is a multi-part message in MIME format. --------------080109070604010609090904 Content-Type: text/plain; charset=ISO-8859-1; format=flowed Content-Transfer-Encoding: 7bit *Update: #1 ESPC Data Center server rack realignment Phase 1 is complete.* Topic: ESPC Data Center server rack realignment Phase 1 Date/Time Issued: November 28, 2012 2000 UTC Product(s) or Data Impacted: GINI-AWIPS, MODIS (Aqua & Terra), AIRS (Aqua), MTSAT on LRIT, EMWIN on LRIT Date/Time of Initial Impact: November 28, 2012 1300 UTC Date/Time of Expected End: November 28, 2012 2000 UTC Length of Activity: 7 hours Details/Specifics of Change: The ESPC Data Center will undergo Phase 1 of a server rack realignment project at NSOF in preparation for future ground segment equipment. A limited number of data products will experience either a short outage or delay. Each system will be returned to operations as soon as possible in order to limit each individual system outage or delay. Here is a listing of impacted products: - Products with redundant systems where no outage or delay is anticipated: GINI-AWIPS - Products to be delayed for up to 8 hours: MODIS (Aqua & Terra), MODIS-derived products, MTSAT on LRIT - Products to be lost with no recovery for up to 8 hours: AIRS (Aqua), EMWIN on LRIT *Update: #1 ESPC Data Center server rack realignment Phase 1 is complete.* Contact Information for Further Information: ESPC Operations at ESPCOperations@noaa.gov and 301-817-3880 Web Site(s) for applicable information: N/A This message was sent from ESPC.Notification@noaa.gov . You have been sent this and other notifications because you have opted in to receive it. For requests to unsubscribe, please contact the ESPC Help Desk atESPCOperations@noaa.gov or (301) 817-3880 . Please note: it make take up to two business days to process your unsubscribe request. --------------080109070604010609090904 Content-Type: text/html; charset=ISO-8859-1 Content-Transfer-Encoding: 7bit
Update: #1   ESPC Data Center server rack realignment Phase 1 is complete.

Topic:  ESPC Data Center server rack realignment Phase 1

Date/Time Issued:  November 28, 2012 2000 UTC

Product(s) or Data Impacted:  GINI-AWIPS, MODIS (Aqua & Terra), AIRS (Aqua), MTSAT on LRIT, EMWIN on LRIT

Date/Time of Initial Impact:  November 28, 2012 1300 UTC

Date/Time of Expected End:  November 28, 2012 2000 UTC

Length of Activity:  7 hours

Details/Specifics of Change:  The ESPC Data Center will undergo Phase 1 of a server rack realignment project at NSOF in preparation for future ground segment equipment.  A limited number of data products will experience either a short outage or delay.  Each system will be returned to operations as soon as possible in order to limit each individual system outage or delay.  Here is a listing of impacted products:
 - Products with redundant systems where no outage or delay is anticipated:  GINI-AWIPS
 - Products to be delayed for up to 8 hours:  MODIS (Aqua & Terra), MODIS-derived products, MTSAT on LRIT
 - Products to be lost with no recovery for up to 8 hours:  AIRS (Aqua), EMWIN on LRIT

Update: #1   ESPC Data Center server rack realignment Phase 1 is complete.

Contact Information for Further Information:  ESPC Operations at ESPCOperations@noaa.gov and 301-817-3880
 
Web Site(s) for applicable information:  N/A
 
This message was sent from ESPC.Notification@noaa.gov.  You have been sent this and other notifications because you have opted in to receive it.  For requests to unsubscribe, please contact the ESPC Help Desk atESPCOperations@noaa.gov or (301) 817-3880. Please note: it make take up to two business days to process your unsubscribe request.
--------------080109070604010609090904--