Subject: Administrative:NSOF Facilities work :Update #2: Shutdown of This is a multi-part message in MIME format. --------------080000010700030406050505 Content-Type: text/plain; charset=ISO-8859-1; format=flowed Content-Transfer-Encoding: 7bit * * *Topic: *Facilities Maintenance requires shutdown of ESPC Test and Development Systems. *Date/Time**Issued:*August 12, 2013 2133 UTC *Product(s) or Data Impacted:*All ESPC *Date/Time of Initial Impact:*August 12, 2013 11:30:00 *Date/Time of Expected End:*TBD ** *Length of Outage:*TBD *Details/Specifics of Change:* Due to facilities maintenance work to repair a failed Uninterruptible Power Supply (UPS), ESPC will need to power down its Test and Development servers in order to reduce the total load on the remaining UPS systems. Power will be restored later today, allowing for restoration of these systems. However, additional work will be required later in the week, which will require the systems to be briefly taken off-line again at that time. More information will be made available as the time schedules are finalized. *Update #2: *Addition work is still being performed to support the NSOF facilities power maintenance. A decision will be made tomorrow morning (August 13) at 1030Z (6:30am) whether or not to proceed with shutting down backup servers in order to reach the required power levels, or if alternative plans need to be invoked. The power work should be completed, and all servers restarted by 1600Z (Noon). Additional power work will require the systems to be shutdown again sometime later in the the week. More information will be made available later. *Update #1*: Efforts continue to support the Facilities power work. Additional power load needs to be removed from the UPS systems. Additional groups are currently powering down their equipment. Facilities is monitoring the power levels and will determine when the appropriate threshold has been met. As the work is taking longer than expected, ESPC DEV and TEST systems will need to remain off-line until tomorrow (August 13) morning. *Contact Information for Further Information:*ESPC Operations at ESPCOperations@noaa.gov and 301-817-3880 . *Web Site(s) for applicable information:*N/A This message was sent by ESPC.Notification@noaa.gov . You have been sent this and other notifications because you have opted in to receive it. If for any reason, you wish to unsubscribe, please contact ESPC Help Desk at ESPCOperations@noaa.gov or (301) 817-3880 . Please note: it may take up to two business days to process your unsubscribe request. --------------080000010700030406050505 Content-Type: text/html; charset=ISO-8859-1 Content-Transfer-Encoding: 7bit
Topic:  Facilities Maintenance requires shutdown of ESPC Test and Development Systems.

Date/Time Issued:  August 12, 2013   2133 UTC

Product(s) or Data Impacted:  All ESPC

Date/Time of Initial Impact: August 12, 2013  11:30:00

Date/Time of Expected End:  TBD

Length of Outage:  TBD

Details/Specifics of Change: Due to facilities maintenance work to repair a failed Uninterruptible Power Supply (UPS), ESPC will need to power down its Test and Development servers in order to reduce the total load on the remaining UPS systems. 


Power will be restored later today, allowing for restoration of these systems.  However, additional work will be required later in the week, which will require the systems to be briefly taken off-line again at that time.  More information will be made available as the time schedules are finalized.

Update #2:  Addition work is still being performed to support the NSOF facilities power maintenance.  A decision will be made tomorrow morning (August 13) at 1030Z (6:30am) whether or not to proceed with shutting down backup servers in order to reach the required power levels, or if alternative plans need to be invoked.

The power work should be completed, and all servers restarted by 1600Z (Noon).

Additional power work will require the systems to be shutdown again sometime later in the the week.  More information will be made available later.

Update #1:  Efforts continue to support the Facilities power work.  Additional power load needs to be removed from the UPS systems.  Additional groups are currently powering down their equipment.  Facilities is monitoring the power levels and will determine when the appropriate threshold has been met.  As the work is taking longer than expected, ESPC DEV and TEST systems will need to remain off-line until tomorrow (August 13) morning.


Contact Information for Further Information: ESPC Operations at ESPCOperations@noaa.gov and 301-817-3880.

Web Site(s) for applicable information: N/A

This message was sent by ESPC.Notification@noaa.gov. You have been sent this and other notifications because you have opted in to receive it. If for any reason, you wish to unsubscribe, please contact ESPC Help Desk at ESPCOperations@noaa.gov or (301) 817-3880. Please note: it may take up to two business days to process your unsubscribe request.