Subject: Product/Anomaly: UPDATE #2 S-NPP IDPS VIIRS EDR Products This is a multi-part message in MIME format. --------------060500060606060305020008 Content-Type: text/plain; charset=ISO-8859-1; format=flowed Content-Transfer-Encoding: 7bit ****Update #2:************Most of missing VIIRS EDR Data was processed in the backorbits of SVL 12415, 12416, 12417, and 12418. We are still waiting for a small bit of VIIRS EDR products to be processed, but due to IDPS queues frozen at this time and recycling in place, the remaining VIIRS EDR data will be reprocessed when IDPS is running nominally.**** Update #1:**** NESDIS IDPS processed orbit 12415 nominally after 10:25Z recycle of NESDIS IDPS OPS string. Currently, IDPS is reprocessing the missing VIIRS EDR data from orbits 12411, 12412, and 12413. This data is being retasked during the backorbits and may take several hours to complete as processing of first copy data is priority. **** *****Topic:* IDPS System not producing higher order VIIRS EDR products *Date/Time Issued:* March 21, 2014 - 1946 UTC *Product(s) or Data Impacted:* VIIRS EDR products *Date/Time of Initial Impact:* March 21, 2014 0210 UTC *Date/Time of Expected End:* TBD *Length of Outage:* TBD *Details/Specifics of Change: * IDPS stopped processing some VIIRS EDR products beginning at 03/21/2014 0210 UTC. The IDPS system is still producing EDR products, but very slowly and all items are not working off VIIRS queue. IDPS engineering was contacted and IDPS system was recycled per System Engineer's request. However, some products have still not been produced. Engineering is coming in to investigate. *Contact Information for Further Information:* ESPC Operations at ESPCOperations@noaa.gov and 301-817-3880* Web Site(s) for applicable information:* N/A You have been sent this and other notifications because you have opted in to receive it. If for any reason, you wish to unsubscribe, please contact ESPC Help Desk at ESPCOperations@noaa.gov or (301) 817-3880. Please note: it may take up to two business days to process your unsubscribe request. --------------060500060606060305020008 Content-Type: text/html; charset=ISO-8859-1 Content-Transfer-Encoding: 7bit Update #2: Most of missing VIIRS EDR Data was processed in the backorbits of SVL 12415, 12416, 12417, and 12418. We are still waiting for a small bit of VIIRS EDR products to be processed, but due to IDPS queues frozen at this time and recycling in place, the remaining VIIRS EDR data will be reprocessed when IDPS is running nominally.


Update #1:
NESDIS IDPS processed orbit 12415 nominally after 10:25Z recycle of NESDIS IDPS OPS string.

Currently, IDPS is reprocessing the missing VIIRS EDR data from orbits 12411, 12412, and 12413.

This data is being retasked during the backorbits and may take several hours to complete as processing of first copy data is priority.

Topic: IDPS System not producing higher order VIIRS EDR products

Date/Time Issued: March 21, 2014 -  1946 UTC

Product(s) or Data Impacted: VIIRS EDR products

Date/Time of Initial Impact: March 21, 2014 0210 UTC

Date/Time of Expected End:  TBD

Length of Outage: TBD

Details/Specifics of Change: 

IDPS stopped processing some VIIRS EDR products beginning at 03/21/2014 0210 UTC. The IDPS system is still producing EDR products, but very slowly and all items are not working off VIIRS queue.

IDPS engineering was contacted and IDPS system was recycled per System Engineer's request. However, some products have still not been produced. Engineering is coming in to investigate.

Contact Information for Further Information: ESPC Operations at ESPCOperations@noaa.gov and 301-817-3880

Web Site(s) for applicable information:
  N/A