Subject: Administrative: Suomi-NPP Drag Make-Up (DMU) Maneuver This is a multi-part message in MIME format. --Boundary_(ID_IaP+Xm8aVlDtX7qWyVxPtQ) Content-type: text/plain; charset=utf-8; format=flowed Content-transfer-encoding: 8BIT *Topic:* S-NPP Drag Make-UP (DMU) Maneuver scheduled for September 8, 2016 *Date/Time Issued:* September 7, 2016 1830Z *Product(s) or Data Impacted:* All S-NPP Sensor Data *Date/Time of Initial Impact:* September 8, 2016 12:00Z *Date/Time of Expected End:* September 8, 2016 22:00Z *Length of Outage:* See Details. * **Details/Specifics of Change:* On September 8, 2016 at 16:00:00Z, S-NPP will perform a 2.0 second propulsive Drag Make-UP (DMU) maneuver to maintain Repeating Ground Track. Due to the DMU activities, some of the ATMS Scan Reversals will not occur. During the period of DMU preparation and activities, ATMS Scan Reversals will be manually commanded to minimize skipped reversals, but may not occur exactly at stepped latitudes and thus small data gaps may be introduced. The following observatory systems will be affected on September 8, 2016. 12:00:00Z – 22:00:00Z ATMS Scan Reversal will be manually commanded, some reversals will be missed. 15:34:00Z – 17:41:04Z CERES in Contam-Safe mode, science data will not be available 15:44:00Z – 16:11:06Z OMPS in Decon mode, Science data will not be available 15:49:00Z - 16:12:04Z HRD will be off, data for direct broadcast users will be unavailable 15:54:00Z – 16:07:04Z S-NPP pointing off-nadir, collected data during that time period may be impacted and not disseminated *Contact Information for Further Information:* ESPC Operations at ESPCOperations@noaa.gov at 301-817-3880 *Web Site(s) for applicable information:* N/A This message was sent to ESPC.Notification@noaa.gov. You have been sent this and other notifications because you have opted in to receive it. If for any reason, you wish to unsubscribe, please contact ESPC --Boundary_(ID_IaP+Xm8aVlDtX7qWyVxPtQ) Content-type: text/html; charset=utf-8 Content-transfer-encoding: 8BIT

Topic:  S-NPP Drag Make-UP (DMU) Maneuver scheduled for September 8, 2016

Date/Time Issued:  September 7, 2016 1830Z

Product(s) or Data Impacted:  All S-NPP Sensor Data

Date/Time of Initial Impact: September 8, 2016  12:00Z

Date/Time of Expected End: September 8, 2016  22:00Z

Length of Outage:  See Details.

Details/Specifics of Change: On September 8, 2016 at 16:00:00Z, S-NPP will perform a 2.0 second propulsive Drag Make-UP (DMU) maneuver to maintain Repeating Ground Track.  Due to the DMU activities, some of the ATMS Scan Reversals will not occur.  During the period of DMU preparation and activities, ATMS Scan Reversals will be manually commanded to minimize skipped reversals, but may not occur exactly at stepped latitudes and thus small data gaps may be introduced.

The following observatory systems will be affected on September 8, 2016.

12:00:00Z – 22:00:00Z  ATMS Scan Reversal will be manually commanded, some reversals will be missed.

15:34:00Z – 17:41:04Z  CERES in Contam-Safe mode, science data will not be available

15:44:00Z – 16:11:06Z  OMPS in Decon mode, Science data will not be available

15:49:00Z - 16:12:04Z  HRD will be off, data for direct broadcast users will be unavailable

15:54:00Z – 16:07:04Z  S-NPP pointing off-nadir, collected data during that time period may be impacted and not disseminated

Contact Information for Further Information: ESPC Operations at ESPCOperations@noaa.gov at 301-817-3880

Web Site(s) for applicable information: N/A

This message was sent to ESPC.Notification@noaa.gov. You have been sent this and other notifications because you have opted in to receive it. If for any reason, you wish to unsubscribe, please contact ESPC


--Boundary_(ID_IaP+Xm8aVlDtX7qWyVxPtQ)--